Original Volume of Soil before Excavation given Percent Swell Solution

STEP 0: Pre-Calculation Summary
Formula Used
Original volume of Soil = (100/(100+0.01*Swell in Soil))*Loaded Volume
VO = (100/(100+0.01*s))*VL
This formula uses 3 Variables
Variables Used
Original volume of Soil - (Measured in Cubic Meter) - Original volume of Soil is the volume of soil before excavation.
Swell in Soil - Swell in Soil is change in volume when subjected to moisture.
Loaded Volume - (Measured in Cubic Meter) - Loaded Volume is the volume of soil after excavation.
STEP 1: Convert Input(s) to Base Unit
Swell in Soil: 5 --> No Conversion Required
Loaded Volume: 25 Cubic Meter --> 25 Cubic Meter No Conversion Required
STEP 2: Evaluate Formula
Substituting Input Values in Formula
VO = (100/(100+0.01*s))*VL --> (100/(100+0.01*5))*25
Evaluating ... ...
VO = 24.9875062468766
STEP 3: Convert Result to Output's Unit
24.9875062468766 Cubic Meter --> No Conversion Required
FINAL ANSWER
24.9875062468766 24.98751 Cubic Meter <-- Original volume of Soil
(Calculation completed in 00.004 seconds)

Credits

Creator Image
Created by Suraj Kumar
Birsa Institute of Technology (BIT), Sindri
Suraj Kumar has created this Calculator and 2200+ more calculators!
Verifier Image
Verified by Ishita Goyal
Meerut Institute of Engineering and Technology (MIET), Meerut
Ishita Goyal has verified this Calculator and 2600+ more calculators!

9 Earth Quantities Hauled Calculators

Original Volume of Soil before Excavation given Percent Swell
​ Go Original volume of Soil = (100/(100+0.01*Swell in Soil))*Loaded Volume
Loaded Volume of Soil given Percent Swell
​ Go Loaded Volume = (Original volume of Soil*(100+0.01*Swell in Soil)/100)
Swell in Soil given Original Volume of Soil
​ Go Swell in Soil = 10000*((Loaded Volume/Original volume of Soil)-1)
Compacted Volume of Soil after Excavation of Soil
​ Go Compacted Volume = (Original volume of Soil*Shrinkage Factor)
Shrinkage Factor using Compacted Volume of Soil
​ Go Shrinkage Factor = (Compacted Volume/Original volume of Soil)
Original Volume of Soil given Compacted Volume
​ Go Original volume of Soil = (Compacted Volume/Shrinkage Factor)
Loaded Volume of Soil given Original Volume of Soil
​ Go Loaded Volume = (Original volume of Soil/Load Factor)
Load Factor given Original Volume of Soil
​ Go Load Factor = (Original volume of Soil/Loaded Volume)
Original Volume of Soil before Excavation
​ Go Original volume of Soil = Loaded Volume*Load Factor

Original Volume of Soil before Excavation given Percent Swell Formula

Original volume of Soil = (100/(100+0.01*Swell in Soil))*Loaded Volume
VO = (100/(100+0.01*s))*VL

What is Volume of Soil?

The total soil volume is the combined volume of solids and pores which may contain air (Vair) or water (Vwater), or both. The average values of air, water and solid in soil are easily measured and are a useful indication of a soils physical condition.

How to Calculate Original Volume of Soil before Excavation given Percent Swell?

Original Volume of Soil before Excavation given Percent Swell calculator uses Original volume of Soil = (100/(100+0.01*Swell in Soil))*Loaded Volume to calculate the Original volume of Soil, The Original Volume of Soil before Excavation given Percent Swell is defined as the volume of soil before excavation when we have the prior knowledge of the percent swell. Original volume of Soil is denoted by VO symbol.

How to calculate Original Volume of Soil before Excavation given Percent Swell using this online calculator? To use this online calculator for Original Volume of Soil before Excavation given Percent Swell, enter Swell in Soil (s) & Loaded Volume (VL) and hit the calculate button. Here is how the Original Volume of Soil before Excavation given Percent Swell calculation can be explained with given input values -> 24.98751 = (100/(100+0.01*5))*25.

FAQ

What is Original Volume of Soil before Excavation given Percent Swell?
The Original Volume of Soil before Excavation given Percent Swell is defined as the volume of soil before excavation when we have the prior knowledge of the percent swell and is represented as VO = (100/(100+0.01*s))*VL or Original volume of Soil = (100/(100+0.01*Swell in Soil))*Loaded Volume. Swell in Soil is change in volume when subjected to moisture & Loaded Volume is the volume of soil after excavation.
How to calculate Original Volume of Soil before Excavation given Percent Swell?
The Original Volume of Soil before Excavation given Percent Swell is defined as the volume of soil before excavation when we have the prior knowledge of the percent swell is calculated using Original volume of Soil = (100/(100+0.01*Swell in Soil))*Loaded Volume. To calculate Original Volume of Soil before Excavation given Percent Swell, you need Swell in Soil (s) & Loaded Volume (VL). With our tool, you need to enter the respective value for Swell in Soil & Loaded Volume and hit the calculate button. You can also select the units (if any) for Input(s) and the Output as well.
How many ways are there to calculate Original volume of Soil?
In this formula, Original volume of Soil uses Swell in Soil & Loaded Volume. We can use 2 other way(s) to calculate the same, which is/are as follows -
  • Original volume of Soil = Loaded Volume*Load Factor