Earliest Expected Occurrence Time of Event j Solution

STEP 0: Pre-Calculation Summary
Formula Used
Earliest Occurrence Time of j = Earliest Occurrence Time of i+Duration of i-j
TEj = TEi+tij
This formula uses 3 Variables
Variables Used
Earliest Occurrence Time of j - (Measured in Day) - The Earliest Occurrence Time of j is the earliest expected occurrence of event j when we consider activity i-j.
Earliest Occurrence Time of i - (Measured in Day) - The Earliest Occurrence Time of i is the earliest expected occurrence of time of event i, when we consider an activity i-j.
Duration of i-j - (Measured in Day) - Duration of i-j is the expected time of activity i-j.
STEP 1: Convert Input(s) to Base Unit
Earliest Occurrence Time of i: 19 Day --> 19 Day No Conversion Required
Duration of i-j: 5 Day --> 5 Day No Conversion Required
STEP 2: Evaluate Formula
Substituting Input Values in Formula
TEj = TEi+tij --> 19+5
Evaluating ... ...
TEj = 24
STEP 3: Convert Result to Output's Unit
2073600 Second -->24 Day (Check conversion here)
FINAL ANSWER
24 Day <-- Earliest Occurrence Time of j
(Calculation completed in 00.004 seconds)

Credits

Created by Chandana P Dev
NSS College of Engineering (NSSCE), Palakkad
Chandana P Dev has created this Calculator and 500+ more calculators!
Verified by Mithila Muthamma PA
Coorg Institute of Technology (CIT), Coorg
Mithila Muthamma PA has verified this Calculator and 700+ more calculators!

17 Project Evaluation and Review Technique Calculators

Optimistic Time given Expected Time
Go Optimistic Time = (6*Mean Time)-(4*Most Likely Time)-Pessimistic Time
Mean or Expected Time
Go Mean Time = (Optimistic Time+(4*Most Likely Time)+Pessimistic Time)/6
Most Likely Time given Expected Time
Go Most Likely Time = (6*Mean Time-Optimistic Time-Pessimistic Time)/4
Standard Deviation given Probability Factor
Go Standard Deviation = (Scheduled Time-Mean Time)/Probability Factor
Scheduled Time given Probability Factor
Go Scheduled Time = (Standard Deviation*Probability Factor)+Mean Time
Expected Time given Probability Factor
Go Mean Time = Scheduled Time-(Standard Deviation*Probability Factor)
Probability Factor
Go Probability Factor = (Scheduled Time-Mean Time)/Standard Deviation
Pessimistic Time given Expected Time
Go Pessimistic Time = 6*Mean Time-Optimistic Time-4*Most Likely Time
Earliest Expected Occurrence Time of Event j
Go Earliest Occurrence Time of j = Earliest Occurrence Time of i+Duration of i-j
Earliest Expected Occurrence Time of Event i
Go Earliest Occurrence Time of i = Earliest Occurrence Time of j-Duration of i-j
Expected Time of Activity i-j
Go Duration of i-j = Earliest Occurrence Time of j-Earliest Occurrence Time of i
Slack of Event i or j
Go Slack of an Event = LOT of Event j-Earliest Occurrence Time of j
Optimistic Time given Standard Deviation
Go Optimistic Time = -(6*Standard Deviation-Pessimistic Time)
Standard Deviation of Activity
Go Standard Deviation = (Pessimistic Time-Optimistic Time)/6
Pessimistic Time given Standard Deviation
Go Pessimistic Time = 6*Standard Deviation+Optimistic Time
Least Allowable Occurrence Time of Event i
Go LOT of Event i = LOT of Event j-Duration of i-j
Least Allowable Occurrence Time of Event j
Go LOT of Event j = LOT of Event i+Duration of i-j

Earliest Expected Occurrence Time of Event j Formula

Earliest Occurrence Time of j = Earliest Occurrence Time of i+Duration of i-j
TEj = TEi+tij

What is Programme Evaluation and Review Technique (PERT)?

It is a numerical technique used in projects in which time cannot be estimated accurately such as research and development projects. It is an event-oriented network. Cost is assumed to be directly proportional to time.
Three time estimates are made in PERT.
1. Optimistic time (to): This is the minimum possible time in which an activity can be completed under the most ideal conditions.
2. Pessimistic time (tp): This is the maximum time required to complete an activity under the worst possible conditions.
3. Most likely time (tm): This is the time required to complete an activity under normal working conditions
Its value lies between to and tp It is near to the expected time.

What is Central Limit Theorem and Critical Path?

Central Limit Theorem: The theorem states that a project consists of a large number of activities, where each activity has its own mean time (te), standard deviation (σ), variance (σ2) and also its own ß-distribution curve.
Critical Path: The time-wise longest path is the critical path. In this path, any type of delay in any event will cause a delay in the project. These are shown by double lines or dark lines in a network.

How to Calculate Earliest Expected Occurrence Time of Event j?

Earliest Expected Occurrence Time of Event j calculator uses Earliest Occurrence Time of j = Earliest Occurrence Time of i+Duration of i-j to calculate the Earliest Occurrence Time of j, The Earliest Expected Occurrence Time of Event j formula is defined as we consider an activity i-j is taking place. EOT is the time at which an event is expected to occur at the earliest. Earliest Occurrence Time of j is denoted by TEj symbol.

How to calculate Earliest Expected Occurrence Time of Event j using this online calculator? To use this online calculator for Earliest Expected Occurrence Time of Event j, enter Earliest Occurrence Time of i (TEi) & Duration of i-j (tij) and hit the calculate button. Here is how the Earliest Expected Occurrence Time of Event j calculation can be explained with given input values -> 0.000278 = 1641600+432000.

FAQ

What is Earliest Expected Occurrence Time of Event j?
The Earliest Expected Occurrence Time of Event j formula is defined as we consider an activity i-j is taking place. EOT is the time at which an event is expected to occur at the earliest and is represented as TEj = TEi+tij or Earliest Occurrence Time of j = Earliest Occurrence Time of i+Duration of i-j. The Earliest Occurrence Time of i is the earliest expected occurrence of time of event i, when we consider an activity i-j & Duration of i-j is the expected time of activity i-j.
How to calculate Earliest Expected Occurrence Time of Event j?
The Earliest Expected Occurrence Time of Event j formula is defined as we consider an activity i-j is taking place. EOT is the time at which an event is expected to occur at the earliest is calculated using Earliest Occurrence Time of j = Earliest Occurrence Time of i+Duration of i-j. To calculate Earliest Expected Occurrence Time of Event j, you need Earliest Occurrence Time of i (TEi) & Duration of i-j (tij). With our tool, you need to enter the respective value for Earliest Occurrence Time of i & Duration of i-j and hit the calculate button. You can also select the units (if any) for Input(s) and the Output as well.
Let Others Know
Facebook
Twitter
Reddit
LinkedIn
Email
WhatsApp
Copied!