Early Finish Time Solution

STEP 0: Pre-Calculation Summary
Formula Used
Early Finish Time = Early Start Time+Safety Stock
EFT = EST+S
This formula uses 3 Variables
Variables Used
Early Finish Time - (Measured in Second) - Early Finish Time is the earliest point in time when the scheduled activity can complete.
Early Start Time - (Measured in Second) - Early Start Time is the earliest point in time when the scheduled activity can begin.
Safety Stock - Safety Stock is the extra stock that is always maintained to mitigate any future risks arising due to stock-outs.
STEP 1: Convert Input(s) to Base Unit
Early Start Time: 19 Day --> 1641600 Second (Check conversion here)
Safety Stock: 2560 --> No Conversion Required
STEP 2: Evaluate Formula
Substituting Input Values in Formula
EFT = EST+S --> 1641600+2560
Evaluating ... ...
EFT = 1644160
STEP 3: Convert Result to Output's Unit
1644160 Second -->19.0296296296296 Day (Check conversion here)
FINAL ANSWER
19.0296296296296 19.02963 Day <-- Early Finish Time
(Calculation completed in 00.004 seconds)

Credits

Created by Suman Ray Pramanik
Indian Institute of Technology (IIT), Kanpur
Suman Ray Pramanik has created this Calculator and 50+ more calculators!
Verified by Akshada Kulkarni
National Institute of Information Technology (NIIT), Neemrana
Akshada Kulkarni has verified this Calculator and 900+ more calculators!

16 Time Estimation Calculators

Expected Waiting Time for Customers in Queue
Go Expected Waiting Time for Customers in Queue = Mean Arrival Rate/(Mean Service Rate*(Mean Service Rate-Mean Arrival Rate))
Standard Normal Variation
Go Standard Normal Variation = (Normal Variate-Expected Value)/Standard Deviation
PERT Expected Time
Go PERT Expected Time = (Optimistic Time+4*Most Likely Time+Pessimistic Time)/6
Time Taken for Manufacturing Model with Shortage
Go Time taken for Manufacturing Model with Shortage = EOQ Manufacturing Model with Shortage/Demand per Year
Independent Float
Go Independent Float = Early Finish Time-Late Start Time-Activity Time
Total Float
Go Total Float = Late Finish Time-(Early Start Time+Activity Time)
Free Float
Go Free Float = Early Finish Time-Early Start Time-Activity Time
Expected Waiting Time for Customers in System
Go Expected Waiting Time for Customers in System = 1/(Mean Service Rate-Mean Arrival Rate)
Time Taken for Purchase Model with No Shortage
Go Time taken for Purchase Model no Shortage = Economic Order Quantity/Demand per Year
Time Taken for Purchase Model with Shortage
Go Time taken for Purchase Model with Shortage = EOQ Purchase Model/Demand per Year
Total Float given Finish Time
Go Total Float given Finish Times = Late Finish Time-Early Finish Time
Standard Deviation given Optimistic and Pessimistic Time
Go Standard Deviation = (Pessimistic Time-Optimistic Time)/6
Independent Float given Slack
Go Independent Float given Slack = Free Float-Slack of Event
Late Finish Time
Go Late Finish Time = Late Start Time+Duration of Activity
Early Finish Time
Go Early Finish Time = Early Start Time+Safety Stock
Total Float given Start Time
Go Total Float = Late Start Time-Early Start Time

Early Finish Time Formula

Early Finish Time = Early Start Time+Safety Stock
EFT = EST+S

What is Early Finish Time?

Early Finish Time is the earliest point in time when the scheduled activity can complete. For its calculation we use the forward pass; we will start from the beginning and proceed to the end. It is equal to the sum of the early start time and the safety stock.

How to Calculate Early Finish Time?

Early Finish Time calculator uses Early Finish Time = Early Start Time+Safety Stock to calculate the Early Finish Time, Early Finish Time is the earliest point in time when the scheduled activity can complete. We use a forward pass for calculating this. Early Finish Time is denoted by EFT symbol.

How to calculate Early Finish Time using this online calculator? To use this online calculator for Early Finish Time, enter Early Start Time (EST) & Safety Stock (S) and hit the calculate button. Here is how the Early Finish Time calculation can be explained with given input values -> 0.00022 = 1641600+2560.

FAQ

What is Early Finish Time?
Early Finish Time is the earliest point in time when the scheduled activity can complete. We use a forward pass for calculating this and is represented as EFT = EST+S or Early Finish Time = Early Start Time+Safety Stock. Early Start Time is the earliest point in time when the scheduled activity can begin & Safety Stock is the extra stock that is always maintained to mitigate any future risks arising due to stock-outs.
How to calculate Early Finish Time?
Early Finish Time is the earliest point in time when the scheduled activity can complete. We use a forward pass for calculating this is calculated using Early Finish Time = Early Start Time+Safety Stock. To calculate Early Finish Time, you need Early Start Time (EST) & Safety Stock (S). With our tool, you need to enter the respective value for Early Start Time & Safety Stock and hit the calculate button. You can also select the units (if any) for Input(s) and the Output as well.
Let Others Know
Facebook
Twitter
Reddit
LinkedIn
Email
WhatsApp
Copied!