Original Volume of Soil before Excavation Solution

STEP 0: Pre-Calculation Summary
Formula Used
Original volume of Soil = Loaded Volume*Load Factor
VO = VL*LF
This formula uses 3 Variables
Variables Used
Original volume of Soil - (Measured in Cubic Meter) - Original volume of Soil is the volume of soil before excavation.
Loaded Volume - (Measured in Cubic Meter) - Loaded Volume is the volume of soil after excavation.
Load Factor - Load Factor is the ratio of average load to the maximum demand during a given period.
STEP 1: Convert Input(s) to Base Unit
Loaded Volume: 25 Cubic Meter --> 25 Cubic Meter No Conversion Required
Load Factor: 0.1 --> No Conversion Required
STEP 2: Evaluate Formula
Substituting Input Values in Formula
VO = VL*LF --> 25*0.1
Evaluating ... ...
VO = 2.5
STEP 3: Convert Result to Output's Unit
2.5 Cubic Meter --> No Conversion Required
FINAL ANSWER
2.5 Cubic Meter <-- Original volume of Soil
(Calculation completed in 00.020 seconds)

Credits

Created by Suraj Kumar
Birsa Institute of Technology (BIT), Sindri
Suraj Kumar has created this Calculator and 2200+ more calculators!
Verified by Ishita Goyal
Meerut Institute of Engineering and Technology (MIET), Meerut
Ishita Goyal has verified this Calculator and 2600+ more calculators!

9 Earth Quantities Hauled Calculators

Original Volume of Soil before Excavation given Percent Swell
Go Original volume of Soil = (100/(100+0.01*Swell in Soil))*Loaded Volume
Loaded Volume of Soil given Percent Swell
Go Loaded Volume = (Original volume of Soil*(100+0.01*Swell in Soil)/100)
Swell in Soil given Original Volume of Soil
Go Swell in Soil = 10000*((Loaded Volume/Original volume of Soil)-1)
Compacted Volume of Soil after Excavation of Soil
Go Compacted Volume = (Original volume of Soil*Shrinkage Factor)
Shrinkage Factor using Compacted Volume of Soil
Go Shrinkage Factor = (Compacted Volume/Original volume of Soil)
Original Volume of Soil given Compacted Volume
Go Original volume of Soil = (Compacted Volume/Shrinkage Factor)
Loaded Volume of Soil given Original Volume of Soil
Go Loaded Volume = (Original volume of Soil/Load Factor)
Load Factor given Original Volume of Soil
Go Load Factor = (Original volume of Soil/Loaded Volume)
Original Volume of Soil before Excavation
Go Original volume of Soil = Loaded Volume*Load Factor

Original Volume of Soil before Excavation Formula

Original volume of Soil = Loaded Volume*Load Factor
VO = VL*LF

What is Volume of Soil?

The total soil volume is the combined volume of solids and pores which may contain air (Vair) or water (Vwater), or both.The average values of air, water and solid in soil are easily measured and are a useful indication of a soils physical condition.

How to Calculate Original Volume of Soil before Excavation?

Original Volume of Soil before Excavation calculator uses Original volume of Soil = Loaded Volume*Load Factor to calculate the Original volume of Soil, The Original Volume of Soil before Excavation is defined as the volume of soil before excavation when load factor and loaded volume is known. Original volume of Soil is denoted by VO symbol.

How to calculate Original Volume of Soil before Excavation using this online calculator? To use this online calculator for Original Volume of Soil before Excavation, enter Loaded Volume (VL) & Load Factor (LF) and hit the calculate button. Here is how the Original Volume of Soil before Excavation calculation can be explained with given input values -> 2.5 = 25*0.1.

FAQ

What is Original Volume of Soil before Excavation?
The Original Volume of Soil before Excavation is defined as the volume of soil before excavation when load factor and loaded volume is known and is represented as VO = VL*LF or Original volume of Soil = Loaded Volume*Load Factor. Loaded Volume is the volume of soil after excavation & Load Factor is the ratio of average load to the maximum demand during a given period.
How to calculate Original Volume of Soil before Excavation?
The Original Volume of Soil before Excavation is defined as the volume of soil before excavation when load factor and loaded volume is known is calculated using Original volume of Soil = Loaded Volume*Load Factor. To calculate Original Volume of Soil before Excavation, you need Loaded Volume (VL) & Load Factor (LF). With our tool, you need to enter the respective value for Loaded Volume & Load Factor and hit the calculate button. You can also select the units (if any) for Input(s) and the Output as well.
How many ways are there to calculate Original volume of Soil?
In this formula, Original volume of Soil uses Loaded Volume & Load Factor. We can use 2 other way(s) to calculate the same, which is/are as follows -
  • Original volume of Soil = (100/(100+0.01*Swell in Soil))*Loaded Volume
  • Original volume of Soil = (Compacted Volume/Shrinkage Factor)