Total Float Solution

STEP 0: Pre-Calculation Summary
Formula Used
Total Float = Late Finish Time-(Early Start Time+Activity Time)
TF0 = LFT-(EST+tactivity)
This formula uses 4 Variables
Variables Used
Total Float - (Measured in Second) - Total float is the period by which an activity can shift its timing without affecting the relevant schedule completion date.
Late Finish Time - (Measured in Second) - Late Finish Time is the latest point in time when the scheduled activity can finish so as not to delay the project completion date or any constraint.
Early Start Time - (Measured in Second) - Early Start Time is the earliest point in time when the scheduled activity can begin.
Activity Time - (Measured in Second) - Activity time is the estimated task duration based on preceding logic and constraints.
STEP 1: Convert Input(s) to Base Unit
Late Finish Time: 57 Day --> 4924800 Second (Check conversion ​here)
Early Start Time: 19 Day --> 1641600 Second (Check conversion ​here)
Activity Time: 20 Day --> 1728000 Second (Check conversion ​here)
STEP 2: Evaluate Formula
Substituting Input Values in Formula
TF0 = LFT-(EST+tactivity) --> 4924800-(1641600+1728000)
Evaluating ... ...
TF0 = 1555200
STEP 3: Convert Result to Output's Unit
1555200 Second -->18 Day (Check conversion ​here)
FINAL ANSWER
18 Day <-- Total Float
(Calculation completed in 00.020 seconds)

Credits

Creator Image
Created by Suman Ray Pramanik
Indian Institute of Technology (IIT), Kanpur
Suman Ray Pramanik has created this Calculator and 50+ more calculators!
Verifier Image
Verified by Akshada Kulkarni
National Institute of Information Technology (NIIT), Neemrana
Akshada Kulkarni has verified this Calculator and 900+ more calculators!

16 Time Estimation Calculators

Expected Waiting Time for Customers in Queue
​ Go Expected Waiting Time for Customers in Queue = Mean Arrival Rate/(Mean Service Rate*(Mean Service Rate-Mean Arrival Rate))
Standard Normal Variation
​ Go Standard Normal Variation = (Normal Variate-Expected Value)/Standard Deviation
PERT Expected Time
​ Go PERT Expected Time = (Optimistic Time+4*Most Likely Time+Pessimistic Time)/6
Time Taken for Manufacturing Model with Shortage
​ Go Time taken for Manufacturing Model with Shortage = EOQ Manufacturing Model with Shortage/Demand per Year
Independent Float
​ Go Independent Float = Early Finish Time-Late Start Time-Activity Time
Total Float
​ Go Total Float = Late Finish Time-(Early Start Time+Activity Time)
Free Float
​ Go Free Float = Early Finish Time-Early Start Time-Activity Time
Expected Waiting Time for Customers in System
​ Go Expected Waiting Time for Customers in System = 1/(Mean Service Rate-Mean Arrival Rate)
Time Taken for Purchase Model with No Shortage
​ Go Time taken for Purchase Model no Shortage = Economic Order Quantity/Demand per Year
Time Taken for Purchase Model with Shortage
​ Go Time taken for Purchase Model with Shortage = EOQ Purchase Model/Demand per Year
Total Float given Finish Time
​ Go Total Float given Finish Times = Late Finish Time-Early Finish Time
Standard Deviation given Optimistic and Pessimistic Time
​ Go Standard Deviation = (Pessimistic Time-Optimistic Time)/6
Independent Float given Slack
​ Go Independent Float given Slack = Free Float-Slack of Event
Late Finish Time
​ Go Late Finish Time = Late Start Time+Duration of Activity
Early Finish Time
​ Go Early Finish Time = Early Start Time+Safety Stock
Total Float given Start Time
​ Go Total Float = Late Start Time-Early Start Time

Total Float Formula

Total Float = Late Finish Time-(Early Start Time+Activity Time)
TF0 = LFT-(EST+tactivity)

What is Total float?

Total float is the period by which an activity can shift its timing without affecting the relevant schedule completion date. Total Float is the schedule flexibility or amount of time that a scheduled activity can be delayed or extended without delaying the project finish date.

How to Calculate Total Float?

Total Float calculator uses Total Float = Late Finish Time-(Early Start Time+Activity Time) to calculate the Total Float, Total float is the period by which an activity can shift its timing without affecting the relevant schedule completion date. Total Float is denoted by TF0 symbol.

How to calculate Total Float using this online calculator? To use this online calculator for Total Float, enter Late Finish Time (LFT), Early Start Time (EST) & Activity Time (tactivity) and hit the calculate button. Here is how the Total Float calculation can be explained with given input values -> 0.000208 = 4924800-(1641600+1728000).

FAQ

What is Total Float?
Total float is the period by which an activity can shift its timing without affecting the relevant schedule completion date and is represented as TF0 = LFT-(EST+tactivity) or Total Float = Late Finish Time-(Early Start Time+Activity Time). Late Finish Time is the latest point in time when the scheduled activity can finish so as not to delay the project completion date or any constraint, Early Start Time is the earliest point in time when the scheduled activity can begin & Activity time is the estimated task duration based on preceding logic and constraints.
How to calculate Total Float?
Total float is the period by which an activity can shift its timing without affecting the relevant schedule completion date is calculated using Total Float = Late Finish Time-(Early Start Time+Activity Time). To calculate Total Float, you need Late Finish Time (LFT), Early Start Time (EST) & Activity Time (tactivity). With our tool, you need to enter the respective value for Late Finish Time, Early Start Time & Activity Time and hit the calculate button. You can also select the units (if any) for Input(s) and the Output as well.
How many ways are there to calculate Total Float?
In this formula, Total Float uses Late Finish Time, Early Start Time & Activity Time. We can use 1 other way(s) to calculate the same, which is/are as follows -
  • Total Float = Late Start Time-Early Start Time