Total Float given Finish Time Solution

STEP 0: Pre-Calculation Summary
Formula Used
Total Float given Finish Times = Late Finish Time-Early Finish Time
TF0finish = LFT-EFT
This formula uses 3 Variables
Variables Used
Total Float given Finish Times - (Measured in Second) - Total Float given Finish Times is the period by which an activity can shift its timing without affecting the relevant schedule completion date.
Late Finish Time - (Measured in Second) - Late Finish Time is the latest point in time when the scheduled activity can finish so as not to delay the project completion date or any constraint.
Early Finish Time - (Measured in Second) - Early Finish Time is the earliest point in time when the scheduled activity can complete.
STEP 1: Convert Input(s) to Base Unit
Late Finish Time: 57 Day --> 4924800 Second (Check conversion here)
Early Finish Time: 46 Day --> 3974400 Second (Check conversion here)
STEP 2: Evaluate Formula
Substituting Input Values in Formula
TF0finish = LFT-EFT --> 4924800-3974400
Evaluating ... ...
TF0finish = 950400
STEP 3: Convert Result to Output's Unit
950400 Second -->11 Day (Check conversion here)
FINAL ANSWER
11 Day <-- Total Float given Finish Times
(Calculation completed in 00.020 seconds)

Credits

Created by Suman Ray Pramanik
Indian Institute of Technology (IIT), Kanpur
Suman Ray Pramanik has created this Calculator and 50+ more calculators!
Verified by Akshada Kulkarni
National Institute of Information Technology (NIIT), Neemrana
Akshada Kulkarni has verified this Calculator and 900+ more calculators!

16 Time Estimation Calculators

Expected Waiting Time for Customers in Queue
Go Expected Waiting Time for Customers in Queue = Mean Arrival Rate/(Mean Service Rate*(Mean Service Rate-Mean Arrival Rate))
Standard Normal Variation
Go Standard Normal Variation = (Normal Variate-Expected Value)/Standard Deviation
PERT Expected Time
Go PERT Expected Time = (Optimistic Time+4*Most Likely Time+Pessimistic Time)/6
Time Taken for Manufacturing Model with Shortage
Go Time taken for Manufacturing Model with Shortage = EOQ Manufacturing Model with Shortage/Demand per Year
Independent Float
Go Independent Float = Early Finish Time-Late Start Time-Activity Time
Total Float
Go Total Float = Late Finish Time-(Early Start Time+Activity Time)
Free Float
Go Free Float = Early Finish Time-Early Start Time-Activity Time
Expected Waiting Time for Customers in System
Go Expected Waiting Time for Customers in System = 1/(Mean Service Rate-Mean Arrival Rate)
Time Taken for Purchase Model with No Shortage
Go Time taken for Purchase Model no Shortage = Economic Order Quantity/Demand per Year
Time Taken for Purchase Model with Shortage
Go Time taken for Purchase Model with Shortage = EOQ Purchase Model/Demand per Year
Total Float given Finish Time
Go Total Float given Finish Times = Late Finish Time-Early Finish Time
Standard Deviation given Optimistic and Pessimistic Time
Go Standard Deviation = (Pessimistic Time-Optimistic Time)/6
Independent Float given Slack
Go Independent Float given Slack = Free Float-Slack of Event
Late Finish Time
Go Late Finish Time = Late Start Time+Duration of Activity
Early Finish Time
Go Early Finish Time = Early Start Time+Safety Stock
Total Float given Start Time
Go Total Float = Late Start Time-Early Start Time

Total Float given Finish Time Formula

Total Float given Finish Times = Late Finish Time-Early Finish Time
TF0finish = LFT-EFT

What is Total float given finish times?

Total float given finish times is the period by which an activity can shift its timing without affecting the relevant schedule completion date. Total Float is the schedule flexibility or amount of time that a scheduled activity can be delayed or extended without delaying the project finish date.

How to Calculate Total Float given Finish Time?

Total Float given Finish Time calculator uses Total Float given Finish Times = Late Finish Time-Early Finish Time to calculate the Total Float given Finish Times, Total float given Finish Time is the period by which an activity can shift its timing without affecting the relevant schedule completion date. Total Float given Finish Times is denoted by TF0finish symbol.

How to calculate Total Float given Finish Time using this online calculator? To use this online calculator for Total Float given Finish Time, enter Late Finish Time (LFT) & Early Finish Time (EFT) and hit the calculate button. Here is how the Total Float given Finish Time calculation can be explained with given input values -> 0.000127 = 4924800-3974400.

FAQ

What is Total Float given Finish Time?
Total float given Finish Time is the period by which an activity can shift its timing without affecting the relevant schedule completion date and is represented as TF0finish = LFT-EFT or Total Float given Finish Times = Late Finish Time-Early Finish Time. Late Finish Time is the latest point in time when the scheduled activity can finish so as not to delay the project completion date or any constraint & Early Finish Time is the earliest point in time when the scheduled activity can complete.
How to calculate Total Float given Finish Time?
Total float given Finish Time is the period by which an activity can shift its timing without affecting the relevant schedule completion date is calculated using Total Float given Finish Times = Late Finish Time-Early Finish Time. To calculate Total Float given Finish Time, you need Late Finish Time (LFT) & Early Finish Time (EFT). With our tool, you need to enter the respective value for Late Finish Time & Early Finish Time and hit the calculate button. You can also select the units (if any) for Input(s) and the Output as well.