Probability Factor Solution

STEP 0: Pre-Calculation Summary
Formula Used
Probability Factor = (Scheduled Time-Mean Time)/Standard Deviation
Z = (Ts-te)/σ
This formula uses 4 Variables
Variables Used
Probability Factor - The probability Factor is a term used to find the probability of a project getting completed in the expected time.
Scheduled Time - (Measured in Day) - Scheduled Time is the time which is made as per the experience and practice by the creator of the project.
Mean Time - (Measured in Day) - Mean Time, also called expected time is the time needed to complete an activity.
Standard Deviation - The Standard Deviation is a measure of how spread out numbers are.
STEP 1: Convert Input(s) to Base Unit
Scheduled Time: 6.7 Day --> 6.7 Day No Conversion Required
Mean Time: 4 Day --> 4 Day No Conversion Required
Standard Deviation: 1.33 --> No Conversion Required
STEP 2: Evaluate Formula
Substituting Input Values in Formula
Z = (Ts-te)/σ --> (6.7-4)/1.33
Evaluating ... ...
Z = 2.03007518796993
STEP 3: Convert Result to Output's Unit
2.03007518796993 --> No Conversion Required
FINAL ANSWER
2.03007518796993 2.030075 <-- Probability Factor
(Calculation completed in 00.006 seconds)

Credits

Created by Chandana P Dev
NSS College of Engineering (NSSCE), Palakkad
Chandana P Dev has created this Calculator and 500+ more calculators!
Verified by Mithila Muthamma PA
Coorg Institute of Technology (CIT), Coorg
Mithila Muthamma PA has verified this Calculator and 700+ more calculators!

17 Project Evaluation and Review Technique Calculators

Optimistic Time given Expected Time
Go Optimistic Time = (6*Mean Time)-(4*Most Likely Time)-Pessimistic Time
Mean or Expected Time
Go Mean Time = (Optimistic Time+(4*Most Likely Time)+Pessimistic Time)/6
Most Likely Time given Expected Time
Go Most Likely Time = (6*Mean Time-Optimistic Time-Pessimistic Time)/4
Standard Deviation given Probability Factor
Go Standard Deviation = (Scheduled Time-Mean Time)/Probability Factor
Scheduled Time given Probability Factor
Go Scheduled Time = (Standard Deviation*Probability Factor)+Mean Time
Expected Time given Probability Factor
Go Mean Time = Scheduled Time-(Standard Deviation*Probability Factor)
Probability Factor
Go Probability Factor = (Scheduled Time-Mean Time)/Standard Deviation
Pessimistic Time given Expected Time
Go Pessimistic Time = 6*Mean Time-Optimistic Time-4*Most Likely Time
Earliest Expected Occurrence Time of Event j
Go Earliest Occurrence Time of j = Earliest Occurrence Time of i+Duration of i-j
Earliest Expected Occurrence Time of Event i
Go Earliest Occurrence Time of i = Earliest Occurrence Time of j-Duration of i-j
Expected Time of Activity i-j
Go Duration of i-j = Earliest Occurrence Time of j-Earliest Occurrence Time of i
Slack of Event i or j
Go Slack of an Event = LOT of Event j-Earliest Occurrence Time of j
Optimistic Time given Standard Deviation
Go Optimistic Time = -(6*Standard Deviation-Pessimistic Time)
Standard Deviation of Activity
Go Standard Deviation = (Pessimistic Time-Optimistic Time)/6
Pessimistic Time given Standard Deviation
Go Pessimistic Time = 6*Standard Deviation+Optimistic Time
Least Allowable Occurrence Time of Event i
Go LOT of Event i = LOT of Event j-Duration of i-j
Least Allowable Occurrence Time of Event j
Go LOT of Event j = LOT of Event i+Duration of i-j

Probability Factor Formula

Probability Factor = (Scheduled Time-Mean Time)/Standard Deviation
Z = (Ts-te)/σ

What is an Event and an Activity?

An event represents the accomplishment of some task. In a network diagram, beginning and ending of an activity are represented as events. Each event is represented as a node in a network diagram. An event does not consume any time or resource. Each network diagram starts with an initial event and ends at a terminal event.
An activity is a physically identifiable part of a project, which consumes both time and resources. Activity is represented by an arrow in a network diagram. The head of an arrow represents the start of activity and the tail of arrow represents its end. Activity description and its estimated completion time are written along the arrow.

What is Central Limit Theorem and Critical Path?

Central Limit Theorem: The theorem states that a project consists of a large number of activities, where each activity has its own mean time (te), standard deviation (σ), variance (σ2) and also its own ß-distribution curve.
Critical Path: The time-wise longest path is the critical path. In this path, any type of delay in any event will cause a delay in the project. These are shown by double lines or dark lines in a network.

How to Calculate Probability Factor?

Probability Factor calculator uses Probability Factor = (Scheduled Time-Mean Time)/Standard Deviation to calculate the Probability Factor, The Probability Factor formula is defined as a term used to find the probability of the occurrence of an event or completion of an event at an expected time. Probability Factor is denoted by Z symbol.

How to calculate Probability Factor using this online calculator? To use this online calculator for Probability Factor, enter Scheduled Time (Ts), Mean Time (te) & Standard Deviation (σ) and hit the calculate button. Here is how the Probability Factor calculation can be explained with given input values -> 2.030075 = (578880-345600)/1.33.

FAQ

What is Probability Factor?
The Probability Factor formula is defined as a term used to find the probability of the occurrence of an event or completion of an event at an expected time and is represented as Z = (Ts-te)/σ or Probability Factor = (Scheduled Time-Mean Time)/Standard Deviation. Scheduled Time is the time which is made as per the experience and practice by the creator of the project, Mean Time, also called expected time is the time needed to complete an activity & The Standard Deviation is a measure of how spread out numbers are.
How to calculate Probability Factor?
The Probability Factor formula is defined as a term used to find the probability of the occurrence of an event or completion of an event at an expected time is calculated using Probability Factor = (Scheduled Time-Mean Time)/Standard Deviation. To calculate Probability Factor, you need Scheduled Time (Ts), Mean Time (te) & Standard Deviation (σ). With our tool, you need to enter the respective value for Scheduled Time, Mean Time & Standard Deviation and hit the calculate button. You can also select the units (if any) for Input(s) and the Output as well.
Let Others Know
Facebook
Twitter
Reddit
LinkedIn
Email
WhatsApp
Copied!