Production Required given Number of Scrapers Needed for Job Solution

STEP 0: Pre-Calculation Summary
Formula Used
Production Required in Scraper Production = Number of Scraper in Scraper Production*Production per Unit
Ps = Ns*Pu
This formula uses 3 Variables
Variables Used
Production Required in Scraper Production - (Measured in Cubic Meter per Second) - Production Required in Scraper Production is the amount of scrap produced.
Number of Scraper in Scraper Production - Number of Scraper in Scraper Production is the number of scrapers needed in the job.
Production per Unit - (Measured in Cubic Meter per Second) - Production per Unit means the volume of scrap produced in a unit time.
STEP 1: Convert Input(s) to Base Unit
Number of Scraper in Scraper Production: 7 --> No Conversion Required
Production per Unit: 11 Cubic Meter per Hour --> 0.00305555555555556 Cubic Meter per Second (Check conversion ​here)
STEP 2: Evaluate Formula
Substituting Input Values in Formula
Ps = Ns*Pu --> 7*0.00305555555555556
Evaluating ... ...
Ps = 0.0213888888888889
STEP 3: Convert Result to Output's Unit
0.0213888888888889 Cubic Meter per Second -->77.0000000000001 Cubic Meter per Hour (Check conversion ​here)
FINAL ANSWER
77.0000000000001 77 Cubic Meter per Hour <-- Production Required in Scraper Production
(Calculation completed in 00.004 seconds)

Credits

Creator Image
Created by Suraj Kumar
Birsa Institute of Technology (BIT), Sindri
Suraj Kumar has created this Calculator and 2200+ more calculators!
Verifier Image
Verified by Ishita Goyal
Meerut Institute of Engineering and Technology (MIET), Meerut
Ishita Goyal has verified this Calculator and 2600+ more calculators!

25 Scraper Production Calculators

Speed at Haul and Return in Miles per Hour given Variable Time
​ Go Speed in Miles per Hour in Scraper Production = (Haul Distance in Feet+Return Distance in Foot in Scraper Production)/(88*Variable Time in Scraper Production)
Variable Time when Haul and Return Distance is in Feet
​ Go Variable Time in Scraper Production = (Haul Distance in Feet+Return Distance in Foot in Scraper Production)/(88*Speed in Miles per Hour in Scraper Production)
Return Distance in Feet given Variable Time
​ Go Return Distance in Foot in Scraper Production = (Variable Time in Scraper Production*88*Speed in Miles per Hour in Scraper Production)-Haul Distance in Feet
Haul Distance in Feet given Variable Time
​ Go Haul Distance in Feet = (Variable Time in Scraper Production*88*Speed in Miles per Hour in Scraper Production)-Return Distance in Foot in Scraper Production
Speed at Haul and Return in Kilometer per Hour given Variable Time
​ Go Speed in Kmph in Scraper Production = (Haul Distance+Return Distance in Meter)/(16.7*Variable Time in Scraper Production)
Return Distance in Meter given Variable Time
​ Go Return Distance in Meter = (Variable Time in Scraper Production*16.7*Speed in Kmph in Scraper Production)-Haul Distance
Haul Distance in Meter given Variable Time
​ Go Haul Distance = (Variable Time in Scraper Production*16.7*Speed in Kmph in Scraper Production)-Return Distance in Meter
Production Required to Determine Number of Scrapers
​ Go Production Required in Scraper Production = (Bank in Scraper Production/Time in Scraper Production in Hour)
Working Time given Production Required
​ Go Time in Scraper Production in Hour = (Bank in Scraper Production/Production Required in Scraper Production)
Quantity given Production Required
​ Go Bank in Scraper Production = (Production Required in Scraper Production*Time in Scraper Production in Hour)
Production Required given Number of Scrapers Needed for Job
​ Go Production Required in Scraper Production = Number of Scraper in Scraper Production*Production per Unit
Trips per Hour given Production of Scrap by Machines
​ Go Trips per Hour = (Production Required in Scraper Production/Load in Scraper Production)
Load Given Production of Scrap by Machines
​ Go Load in Scraper Production = (Production Required in Scraper Production/Trips per Hour)
Production of Scrap by Machines
​ Go Production Required in Scraper Production = (Load in Scraper Production*Trips per Hour)
Number of Scrapers Needed for Job
​ Go Number of Scraper = (Production Required in Scraper Production/Production per Unit)
Density of Material given Quantity of Scrap Produced
​ Go Density of Material in Scraper Production = (Weight of Load Scrap/Bank in Scraper)
Weight of Load Given Quantity of Scrap Produced
​ Go Weight of Load Scrap = (Bank in Scraper*Density of Material in Scraper Production)
Bank or Quantity of Scrap Produced
​ Go Bank in Scraper = (Weight of Load Scrap/Density of Material in Scraper Production)
Scraper Cycle Time given Number of Scrapers Pusher can Load
​ Go Scraper Cycle Time = (Number of Scraper a Pusher*Pusher Cycle Time)
Pusher Cycle Time given Number of Scrapers Pusher can Load
​ Go Pusher Cycle Time = (Scraper Cycle Time/Number of Scraper a Pusher)
Number of Scrapers Pusher can Load
​ Go Number of Scraper a Pusher = (Scraper Cycle Time/Pusher Cycle Time)
Working Time given Trips per Hour for Excavating Scrap
​ Go Working Time in Scraper Production = (Trips per Hour*Cycle Time)
Cycle Time given Trips per Hour for Excavating Scrap
​ Go Cycle Time = (Working Time in Scraper Production/Trips per Hour)
Trips per Hour for Excavating Scrap
​ Go Trips per Hour = (Working Time in Scraper Production/Cycle Time)
Production per Unit Given Number of Scrapers Needed for Job
​ Go Production per Unit = (Production Required/Number of Scraper)

Production Required given Number of Scrapers Needed for Job Formula

Production Required in Scraper Production = Number of Scraper in Scraper Production*Production per Unit
Ps = Ns*Pu

What is Production?

Production is a process of combining various material inputs and immaterial inputs (plans, know-how) in order to make something for consumption (output). It is the act of creating an output, a good or service which has value and contributes to the utility of individuals.

How to Calculate Production Required given Number of Scrapers Needed for Job?

Production Required given Number of Scrapers Needed for Job calculator uses Production Required in Scraper Production = Number of Scraper in Scraper Production*Production per Unit to calculate the Production Required in Scraper Production, The Production Required given Number of Scrapers Needed for Job is defined as the production of scrap when number of scraper and production per unit is known. Production Required in Scraper Production is denoted by Ps symbol.

How to calculate Production Required given Number of Scrapers Needed for Job using this online calculator? To use this online calculator for Production Required given Number of Scrapers Needed for Job, enter Number of Scraper in Scraper Production (Ns) & Production per Unit (Pu) and hit the calculate button. Here is how the Production Required given Number of Scrapers Needed for Job calculation can be explained with given input values -> 277200 = 7*0.00305555555555556.

FAQ

What is Production Required given Number of Scrapers Needed for Job?
The Production Required given Number of Scrapers Needed for Job is defined as the production of scrap when number of scraper and production per unit is known and is represented as Ps = Ns*Pu or Production Required in Scraper Production = Number of Scraper in Scraper Production*Production per Unit. Number of Scraper in Scraper Production is the number of scrapers needed in the job & Production per Unit means the volume of scrap produced in a unit time.
How to calculate Production Required given Number of Scrapers Needed for Job?
The Production Required given Number of Scrapers Needed for Job is defined as the production of scrap when number of scraper and production per unit is known is calculated using Production Required in Scraper Production = Number of Scraper in Scraper Production*Production per Unit. To calculate Production Required given Number of Scrapers Needed for Job, you need Number of Scraper in Scraper Production (Ns) & Production per Unit (Pu). With our tool, you need to enter the respective value for Number of Scraper in Scraper Production & Production per Unit and hit the calculate button. You can also select the units (if any) for Input(s) and the Output as well.
How many ways are there to calculate Production Required in Scraper Production?
In this formula, Production Required in Scraper Production uses Number of Scraper in Scraper Production & Production per Unit. We can use 2 other way(s) to calculate the same, which is/are as follows -
  • Production Required in Scraper Production = (Load in Scraper Production*Trips per Hour)
  • Production Required in Scraper Production = (Bank in Scraper Production/Time in Scraper Production in Hour)
Let Others Know
Facebook
Twitter
Reddit
LinkedIn
Email
WhatsApp
Copied!